Town hall — this Thursday July 23 · 7:00 p.m. Hallam Auditorium, 315 Main Street. Come hear it firsthand and bring your questions.
HALLAM SAYS NODATA CENTER ZONING CHANGE What you can do

They can pass this in one night.

The Village Board is being asked to write "data center" permanently into Hallam's zoning code. Under this board's normal practice, that ordinance can be introduced and given final passage at the same meeting — no second reading, no second chance. If you wait to see how the first vote goes, there is no second vote.

Days until the Board vote
3
Yes votes is all it takes to pass
15
Ordinances this board passed in one night on June 1
420M
Gallons a year already permitted at this site
Read this part twice

There may be no second reading

Nebraska law normally requires an ordinance to be read on three separate dates before it passes. That rule can be waived by a vote of the board — and this board waives it as routine practice.

At the June 1, 2026 meeting, the board introduced fifteen ordinances, voted to "waive the statutory rule requiring reading on three separate dates," and passed all fifteen the same night. Every vote was 5–0.

Assume this ordinance gets introduced and finally passed at a single meeting. Everything — the phone calls, the turnout, the testimony — has to happen BEFORE that gavel.

The practical deadline is not the vote. It's the meeting before the vote.

Phase 1 is the door. Phase 2 is what walks through it — and we are fighting both.

Our position

Vote no on the zoning amendment

That's it. That's the ask. Not a delay, not a compromise, not a list of conditions — a no vote on September 14, and then real rules written before anyone comes back.

Why no is the only responsible vote
REASON ONE

They haven't given you the numbers

No confirmed power draw. No water figure. No cooling method. No noise study. No removal bond. Hallam's own code says the burden of proof is on the applicant — and it hasn't been met.

REASON TWO

Hallam has no rules for this

Our code doesn't define a data center, set a setback for one, or say a word about its water or its cleanup. Twelve-plus Nebraska counties paused this year to write those rules first. Our comprehensive plan is from 2011.

REASON THREE

It reaches past this project

This changes the code itself, not one site. Depending on which districts it names, it could open farm ground to industrial use permanently — with no hearing and no vote the next time. That is too much to decide in one night.

Three of five trustees can pass this. Two persuaded trustees stop it. We are working all five, and we are asking every one of them for the same thing: vote no.

Still unanswered

Six things nobody has told us

No trustee should vote on a permanent change to our code while these are blank.

QuestionStatus
How many megawatts will it draw?Not confirmed
How many gallons of water per day?Not disclosed
How large is Phase 2?Not disclosed
Measured noise levels at the nearest homes?Not disclosed
Who pays to remove it if it's abandoned?Not disclosed
What tax incentives are being sought?Not disclosed
Why the megawatt number decides the rest Nebraska's 2026 data center law places real duties on facilities at or above ten megawatts: public reporting of electricity and water use, responsibility for decommissioning costs, and a community benefit agreement. Materials presented to residents in July described roughly 28 modular units; published reporting puts that product at about one megawatt each. If that's right, those duties already apply. The applicant has not confirmed the figure — which is itself the point.
Their own evidence

A vote for ten acres is not a vote for ten acres

This is the clearest reason to vote no on the amendment itself — and it comes from the materials Monolith presented to residents, not from us.

In those materials, the operator's Iceland facility is offered as a reason for confidence. The detail given is that it scaled from 33 megawatts to 57 megawatts as demand grew.

That's not our claim about expansion. That's their case study.

The modular design is marketed on exactly this quality — units arrive prefabricated and get added as demand requires. That's a sound business model, and nobody should fault them for it. But it means the ten acres in front of the Board is a starting point, not a ceiling. The only moment a community gets to set that ceiling in writing is before the first approval, not after.

Approving the door is approving what comes through it.

From the Village's own minutes

What's already been done

Everything below comes from the Village of Hallam's published board minutes and agendas. Read together, they show a project moving steadily through our village for months — while still being described publicly as undecided.

April 6, 2026 · Board meeting

The board votes to survey a street easement across Monolith land

Long-term planning for a second route out of town, east toward 42nd Street. The minutes record that Monolith agreed if it involves land they own, and that a survey was needed — 70 feet requested. Approved 5–0. Also discussed: identifying land for a future well site "should we ever need one."

Why it mattersHallam's possible second exit road and its future water options both run across ground controlled by the applicant. Not an accusation — just a fact five trustees carry into the room.
April 22–23, 2026 · Auditorium bookings

An engineering firm starts renting the village meeting room

Burns & McDonnell booked the room, then asked for ongoing standing approval with a rolling deposit. They appear again in May.

Why it mattersFirms don't set up recurring local meeting space for projects that are still hypothetical. [Who they're working for is unconfirmed — ask.]
May 4, 2026 · Board meeting

"Monolith looking at data centers, but no decisions have been made"

The Chairman summarized: 2025 was a bad year, the company sought investors to expand the carbon black plant and did not get them, so it changed direction — one reactor built of twelve planned, now needing four more, construction running to 2030.

Why it mattersIn May the village was told nothing was decided. Four weeks later a named partner was in the room. Ask the board when they actually knew.
June 1, 2026 · Board meeting

Crusoe is named. A road is offered. Fifteen ordinances pass in one night.

Monolith brought new leadership to the board. Per the minutes, the CEO "thanked the village board for being supportive." The minutes also record that the company Monolith may partner with "has an interest in paving 42nd street to the Sprague highway," and that Monolith is willing to let the village use their property to test for another well site.

In the same meeting, the board introduced fifteen ordinances, waived the three-separate-readings requirement, and gave them all final passage. 5–0.

Why it mattersBenefits are being floated informally — a paved road, land for a village well — with nothing in writing. And the board demonstrated exactly how fast an ordinance becomes law here.
June 29, 2026 · Health Department

A room is booked for an air quality permit hearing

The June minutes list an auditorium rental by the Lincoln-Lancaster County Health Department, 6–8 p.m., "anticipating a Public Hearing need on an air quality construction permit."

Why it mattersA second regulatory track with its own public comment. Under Hallam's code (§11-603(G)), that permit is required before a building permit can issue.
July 6, 2026 · Board meeting

Monolith presents. No ordinance on the agenda yet.

Monolith appeared under "Petitions–Communications–Citizens Concern," where the agenda states no action can be taken. The agenda lists "RESOLUTIONS & ORDINANCES: NONE."

Why it mattersAs of July 6 no ordinance had been introduced. The introduction — and possibly the final vote — is still ahead of us.
July 7–22, 2026 · Auditorium bookings

A construction contractor books the room, then weekly

Baker Construction, Power & Process reserved the meeting room July 7–22, then asked to use it one day each week "while here" — for drug testing, CPR, and general meetings.

Why it mattersCrew onboarding and drug testing are late-stage activities, not exploratory ones.
Ahead · The decision points

What's still coming

Aug. 3 — regular board meeting.
Aug. 19 — reported target for the Planning Commission hearing and vote.
Sept. 14 — next regular board meeting. Earlier reporting cited September 7, but the Village's own published calendar lists September 14. September 7 is Labor Day.

Why it mattersConfirm the date and agenda with the Village Clerk every week. An ordinance can appear with 24 hours' notice and be law that night.
What we haven't seen The Village posts only the most recent months online. Minutes before April 2026, and all Planning Commission minutes, are not published — but the Village states they're available on request. Those Planning Commission records are the biggest remaining gap and someone should request them this week.
What we know

The land, and the rules that govern it

From Hallam's zoning ordinance (Village Code Chapter 11), the Lancaster County Assessor, and public reporting. The details matter, because this is where it gets fought.

The Phase 1 site

Monolith's Olive Creek campus on SW 42nd Street, about half a mile north of the village. Roughly ten acres on the northeast portion, on ground already zoned for industry.

Who decides

Section 11-204: the Village Board controls zoning for all land inside the village and within one mile of it. This is a village decision, not a county one.

What's being changed

Section 11-104(B): uses "may be added to a district upon application by a landowner and upon proper amendment of the district regulations." The change attaches to an entire zoning district — not to one parcel.

The Phase 2 ground

The parcel east of the campus is zoned AG — Agriculture District, classed as agricultural and unimproved, per Lancaster County Assessor records. It was acquired by a Lincoln limited liability company in August 2025.

Because it's zoned agricultural, a data center there requires its own rezoning — with a hearing, notice to neighbors, and a vote. Unless this amendment takes that away.

This is why the districts named in the amendment matter so much. If agricultural ground is included, the next expansion out here arrives as an administrative site plan review — no hearing that matters, no notice to neighbors, no vote. Nobody should be asked to give that up in a single meeting, which is reason enough to vote no.

The best argument in their own code

They don't actually need this amendment

Hallam's ordinance already contains a mechanism for exactly this situation. Sections 11-604(B)(14) and 11-605(B)(33) allow the Village Board to approve "any similar use that is determined by the Village Board of Trustees after referral to and recommendation by the Planning Commission to be of an industrial nature similar to the above listed uses."

The board can already consider this one project, on its own merits, without writing "data center" into our code forever. Ask them why they won't.

Water

The number nobody has mentioned

There is already a very large permitted groundwater draw at this site. In 2021 the Lower Platte South Natural Resources District approved three wells at Olive Creek estimated to pump about 420 million gallons a year, used primarily for cooling. That was approved after nearly a year of testing and study.

THE RANGE

Two cooling designs, wildly different

A data center cooled by evaporation runs roughly 2.6 million gallons per megawatt per year. One closed-loop campus reports peak use around 22,000 gallons a day — against about 5,000,000 a day for a comparable evaporative campus.

Same size facility. The difference is a design decision, and right now it is unwritten.

THE MATH

What that would mean here

If Phase 1 is near 28 megawatts and used evaporative cooling, that's roughly 73 million gallons a year — on top of what's already permitted, and something like eight times the water every household in Hallam uses combined.

If it's genuinely closed-loop, it's a rounding error. Nobody will tell us which.

These are our estimates, and we've shown our work The 420 million gallon figure is from the Natural Resources District's own 2021 permit approval. The per-megawatt and closed-loop figures come from published industry reporting. The 28-megawatt figure is our estimate from the module count presented to residents. The village household comparison assumes typical residential use for 268 people. We would genuinely rather be corrected with real numbers than rely on estimates — which is the entire point.
The commitment that isn't one

"Either air-cooled or closed-loop"

That's what residents have been told. It sounds reassuring, and it isn't a commitment. "Either/or" reserves both options and promises neither. It was said to a news station, not written into a permit. And "closed loop" is used loosely in this industry — many systems described that way still reject heat through an evaporative tower that consumes water continuously.

If the plan really is closed-loop, there is no reason not to write it into the permit. Refusing to is the answer.

The water ask

Give us the same process Monolith got

Before those 2021 wells were approved, the Natural Resources District commissioned an independent review of the groundwater modeling, held a public open house in Hallam, held a separate public input session, and took written comment. It then attached conditions: flowmeters on every well, quarterly reporting, groundwater monitoring before and after startup, and authority to add requirements if the operation diverged from the application.

That was good enough for their own wells five years ago. It should be good enough now.

  • Disclose before deciding: peak megawatts, cooling method, projected annual water use, and maximum daily withdrawal.
  • Dry or fully closed-loop cooling written into the permit, with no evaporative heat rejection anywhere in the system.
  • An enforceable cap on maximum daily withdrawal, metered, reported quarterly.
  • Baseline monitoring of neighboring wells before operations begin.
  • An independent review and a public input session — the 2021 standard.
One thing to understand about the Natural Resources District It is not a veto. Under its own rules, if the district finds no detrimental effect on the aquifer or on nearby wells, the permit "shall be granted." Showing up angry does not stop a well permit — evidence does. That's why neighbors with their own wells matter more here than anyone else, and why an independent hydrologist is worth more than a full room.
Noise

The limit on paper isn't the limit you'll live with

Hallam's code does set a noise limit. Section 11-603(E) caps industrial noise at 55 Leq where the receiving property is residential, measured at the property line nearest the source. For scale, 55 is about steady rain, or a conversation ten feet away. A vacuum cleaner is around 70 — and because decibels aren't a straight scale, that's roughly three times as loud, not a little louder.

PROBLEM ONE

The same board that sets a limit can raise it

The 55 Leq standard is just another line in the same ordinance being amended right now. Nothing makes it permanent. A future board can raise it, write an exception, or grant relief — through the same process being used to add "data center" in the first place.

PROBLEM TWO

Enforcement is a bill the village pays

A limit only means something if somebody measures it. Who drives out at 2 a.m. with a sound meter? Who buys the meter, hires the consultant, pays the attorney when a violation is disputed? Those costs land on a village with a general fund of roughly $344,000.

A promise you have to sue someone to collect isn't a protection. It's a hope.

So what should we ask for instead? Conditions that don't depend on the village policing them later: a hard setback distance written into the permit, mandatory noise testing after construction paid for by the applicant with a required fix if it fails, and money posted up front to cover enforcement and removal. Distance and bonds enforce themselves.
Other levers in the same chapter

What the board can require, if it won't deny

  • §11-602(D): a site plan must be filed for every industrial use, and "the Village Board of Trustees may require additional standards as are necessary… for the maximum protection of the environment and the health and safety of the citizens of the village." Explicit authority to impose conditions.
  • §11-1302: a zoning amendment application must state "the names and addresses of all persons having legal or equitable interest in the property." If anyone holds an option or purchase agreement on nearby ground, that should be on the record.
  • §11-1304: "The burden of proof for any zoning change shall be upon the applicant." Not on us.
  • §11-603(G): a Lincoln-Lancaster County Health Department air permit is required before a building permit issues.
  • §11-110(E)(2): an industrial yard adjacent to residential use must be increased to 75 feet with screening — a floor, not a ceiling. Other communities have negotiated data center setbacks of 500 to 1,500 feet.
Before anything else

Town hall — Thursday, July 23, 7:00 p.m.

Hallam Auditorium, 315 Main Street. This is the first chance to hear it directly and ask questions in front of your neighbors. If you do one thing on this page, do this one.

Bring these questions, and write down the answers:

  • How many megawatts is Phase 1, and does that put it over ten?
  • How many gallons of water a day, and is the cooling closed-loop or evaporative?
  • How many acres is Phase 2, and which zoning districts does the amendment name?
  • Who pays to remove it if it's shut down or abandoned?

Be courteous, be specific, and get the answers in front of witnesses. Anything said at a public meeting is something we can hold to.

Find yourself on this list

Exactly what to do, based on who you are

Not opinions — assignments. Most take under fifteen minutes.

If you live in the Village of Hallam

Call one trustee. Then fill the room.

Three of five can pass this. Two persuaded trustees stop it. These are neighbors — be courteous, be specific, write down what they say.

TrusteeCommitteeTerm ends
Gary Vocasek — ChairmanFinance / Personnel2026
Jason BurianekPark / Auditorium2026
Brad NiemeyerUtilities2028
Sheila TaylorPublic Safety2028
Bob WinkStreets2028
  1. Ask them to vote no. That's the whole call. The reason: no megawatt figure, no water figure, no noise study, no removal bond, and no rules on the books yet.
  2. Ask how they intend to vote, then thank them either way and send us the answer.
  3. Ask one more thing: "Will you commit to three separate readings instead of passing it in one night?" It costs them nothing to say yes, and it buys us a month.
  4. Show up. Hallam Auditorium, 315 Main Street, 7:00 p.m. An empty room reads as consent.
Two trustees is the entire margin.
If a trustee tells you they're voting yes Don't argue. Ask them this instead: "Then will you at least keep agricultural ground out of it, so farm land still gets a hearing and a vote before anything is built there?" Write down what they say and get it to us. That answer matters a great deal, and it's the kind of thing a trustee will say to a neighbor on the phone that they won't say at a microphone.
If you own ground out by the site

Your rights depend on this vote

Nebraska law lets the owners of 20% of the land next to a proposed zoning change file a formal protest, forcing four of five trustees instead of three. That protection exists for a future rezoning of agricultural ground — and disappears if this amendment reaches those districts.

  1. Get in touch now so we can map qualifying parcels and acreage before there's a deadline. The threshold is 20% of land area, not 20% of owners.
  2. Confirm you're the owner of record with the Lancaster County Assessor. Trusts, LLCs, and estates need the right signer.
  3. If you have a well, tell us. Effects on nearby wells are the legal standard at the Natural Resources District. Your well is evidence.
  4. Come to the meeting and say out loud that you want agricultural ground left out of the amendment.
This vote decides whether you ever get a say.
If you farm or live in the township

Water is your ground to fight on

Groundwater here is regulated by the Lower Platte South NRD, and large wells need a permit. In 2021 that board put flowmeters, quarterly reporting, and monitoring on the existing wells after a year of study and two public meetings.

  1. Call LPSNRD at (402) 476-2729. Ask whether any well permit application has been filed, and whether the 2021 permits already cover data center use.
  2. Ask to be notified when anything opens for public comment.
  3. Demand metering, aquifer testing, and quarterly reporting as conditions.
If the old permits already cover it, there may be no water hearing at all.
If you can spare an hour and a phone

Go get the documents

Under the Nebraska Public Records Act (§84-712) the village must respond within four business days.

  1. The filed application and the exact amendment text — including which districts it names. Village Clerk, (402) 787-0505. Everything on this site turns on that paragraph.
  2. All Planning Commission minutes and agendas, 2025–2026. Not online. Nobody on our side has read them.
  3. Zoning Chapter 11, Article 13 — the local amendment and protest procedure.
  4. The §11-1302 ownership disclosure filed with the application.
Facts win hearings. Somebody has to go get them.
How we conduct ourselves Courteously, with every official and every employee. Monolith has been part of this community for years and we are not against business or jobs. We're asking that a permanent industrial use not be written into our code before anyone will tell us how big it gets, how loud it is, how much water it takes, or who cleans it up — and that farm ground keep the protections it has today. Stick to the sourced facts on this page. A single wrong number costs us more than it buys.